No.,Financial and Activity Report (sheet 2 of 2), ,Major Completed Actions (short bulleted list of the major actions taken in the last week),Major Planned Actions (short bulleted list of the major planned actions in the last week) 1,CBP:,CBP: 2,- Mobile Surveillance Capability (MSC) project: Source Selection Advisory Committee (SSAC) met on 11/19 and 11/22/2010.,"- Mobile Surveillance Capability (MSC) project: This contract had been under protest, which delayed the award. Source Selection Advisory Committee (SSAC) met on 11/19 and 11/22/10. However, SSAC requires additional time to complete actions from the review. Source Selection Authority (SSA) meeting has been rescheduled to early December." 3,"- CBP expended approximately $500,300 for CBP executed port modernization activities during the week of 11/22/2010.","- CBP continues to coordinate with DHS and Canada Border Services Agency (CBSA) regarding the potential port closure at Churubusco, NY/Franklin Centre, Quebec." 4,- Tactical Communications - No new major completed actions to report this week. Non-Intrusive Inspection (NII): - No new major completed actions to report this week.,"- Tactical Communications: - No major planned actions to report this week. Non-Intrusive Inspection (NII): - On 11/30/2010, CBP plans to award a contract for two Low Energy Drive Through Portal Systems. The Request for Proposal for this award was under protest, which delayed the award. The protest was withdrawn on 8/30/2010." 5,DHS MGMT - The increase in outlays was due to the payment for Security Team equipment received. Provided comments back to GSA on the Preliminary Draft Environmental Impact Statement (EIS) for the East Campus Master Plan amendment detailing the FEMA occupancy.,"DHS MGMT - GSA will hold a kick-off meeting for the Technology Integration Program (TIP) re-procurement on Dec 2nd, 2010. The excavation of 1.6 million cubic yards of soil for the U.S. Coast Guard Headquarters will be completed by the end of November 2010. The next Section 106 Consulting Parties Meeting will be held on December 14th, 2010. The Draft Environmental Impact Statement for the East Campus Draft Master Plan Amendment is scheduled to be released for public comment on December 17th, 2010." 6,ICE:,ICE: 7,"- Atlas Tactical Communications Regions 2/3 Project 25 (P25) Upgrade contractor completed Region 2 (Boston Region) phase 1 radio site surveys on November 12, 2010","- Atlas Tactical Communications Regions 2/3 P25 Upgrade contractor plans to initiate Region 3 (Denver Region) radio site surveys on November 29, 2010" 8,- Atlas Tactical Communications Regions 2/3 P25 Upgrade contractor delivered a Region 2 (Boston Region) site survey report for the phase 1 radio sites on November 18. 2010,"- Atlas Tactical Communications Technical Maintenance Facility (TMF) P25 Hub Upgrade contractor plans to conduct a meeting to review the hub system design on December 1, 2010" 9,,"- Atlas Tactical Communications TMF P25 Hub Upgrade contractor plans to complete a hub system design document by December 10, 2010" 10,"NPPD - Currently, GSA has provided funding and properly executed agreements for $15.4 Million. $915K of this is currently working through the procurement process.",NPPD 11,"TSA - Outlays increased by approximately $6.6M. This increase is attributable to technology contracts for AIT ($6.4M) and BLS ($168.1K) units, as well as an independent verification and validation contract ($155).",TSA ,, ,, ,,